Dawlish HIF is the construction of a new 26m span bridge and 110m of carriageway on the embankment, including construction of footways and cycleways, with a further 360m of 6m carriageway. 

The new link road and an associated bridge over Shutterton Brook is part of a wider scheme for 860 homes near Secmaton Lane. This project is contained in Teignbridge District Councils current local plan and is a key step in achieving the goal of linking Elm Grove Road and the A379 Exeter Road.

Montel was appointed by Devon County Council following a traditional tender process, while developing site specific contractor design elements including significant ground stabilisation works.

£ 1 m
0 months
Montel

Integrated Delivery Team

Montel was appointed by Devon County Council following a traditional tender process, while developing site specific contractor design elements including significant ground stabilisation works.

  • The works included:
  • Site preparation and clearance
  • Sheet piling to prepare the area for the installation of the bridge
  • Draining works including surface water and attenuation features
  • Installation of a foul water network
  • Bridge installation
  • Constuction of carriageway, footways and cycleways
  • Landscaping
  • Fencing 
Montel

Adopting a Resilient & Sustainable Strategy

Embodied Carbon reduction:

  • Reduced material usage
    • Optimised design, non–steel safety barrier, earth embankments
    • Concrete optimisation
  • Material reuse
    • Temporary stone reuse
  • Cement replacements
    • Recycled constituents
  • Locally sourced materials
    • Local quarried materials
  • Low maintenance
    • No bearings, no expansion joints, galvanised parapets
  • Long lifespan materials
Montel

Social Value at Our Core

Montel placed Social Value at the core of this project, creating a new role for Rhys as a labourer. Supporting his career goals, Montel helped him enrol on a five-year Civil Engineering Degree Apprenticeship at Exeter University.

Community Engagement:

  • Montel kept the community updated on the progress of the works. We regularly posted newsletter updates on our website and social media outlets
  • Our community board also offered updates on the progress of the works
  • Our QR posters on fencing around the site offers a quick way to scan through to our dedicated project page on our website for updates