Phase 5 Infrastructure, Emerson’s Green

Gallery

Project Detail

CLIENT Emerson’s Green Urban Village Limited
ENGINEER Phoenix Design Partnership
PROJECT MANAGER Gardiner & Theobald LLP
ADOPTING AUTHORITY South Gloucestershire Council
CONTRACT VALUE £3m
CONTRACT DURATION 56 Weeks
PROJECT STATUS Complete
WORKS COMPRISE
  • Earthworks
  • Foul and storm water drainage
  • Roads
  • Excavation and information of balancing pond
  • Infrastructure
  • Installation of services
  • Multi-plate steel culvert structures

Share Our Work