Phase 1 Consortium Works, Heyford Park

Gallery

Project Detail

CLIENT Dorchester Living / Bovis Homes
ENGINEER Woods Harwick
ADOPTING AUTHORITY Oxfordshire County Council
CONTRACT VALUE £1.9m
CONTRACT DURATION 40 Weeks
PROJECT STATUS Complete
WORKS COMPRISE
  • 588m Storm water sewer diversion
  • New footway diversions
  • 1800mm communal service trench
  • Existing road reinstatements
  • 4000m HV Ducting
  • Pedestrian and Traffic management
  • 265m S278 Upgrade of Camp Rd
  • Utility Installations