Parkfield Water Course, Emersons Green

Gallery

Project Detail

CLIENT: Emerson’s Green Urban Village Limited
ENGINEER Phoenix Design Partnership
PROJECT MANAGER Gardiner & Theobald LLP
CONTRACT VALUE £180k
CONTRACT DURATION 12 Weeks
PROJECT STATUS Complete
WORKS COMPRISE
  • Widening of existing watercourse
  • Increased storage capacity
  • Protection to new housing
  • 1600m3 Excavation
  • Working within a watercourse
  • Anti-siltation measures
  • PCC headwalls & trash screens
  • Temporary flow management

Client